Construction Updates

Please review our list of current construction projects.  We will provide updates periodically for each project.  You can contact the Engineering department with any questions you may have.  We can be reached at 307-235-8341.


Robertson Road North Pathway           
Robertson Road Pathway facing north Location: North on Robertson Road from Squash Blossom Road 
Consultant/Contractor: WWC
Start Date: TBD
Expected Completion Date: TBD
Status: Design is complete with easement negotiations ongoing.
Cost and Funding Source: $420,000 - WYDOT Tap allocation and Platte River Parkway Trust One Cent allocation
Project includes installation of a new 10-foot wide concrete pathway to be constructed along Robertson Road from Squash Blossom Road north to the City of Casper's growth boundary (approx. 3500 linear feet).

Currently negotiating easements which are required to be in place prior to beginning construction.

August 25th:  Currently Redesigning project

January 16th:  Design documents being reviewed by WYDOT.



Fire Station #6           

           
Location: Corner of Iris Street and Valley Drive
Consultant/Contractor: GSG Architecture
Caspar Building Systems, Inc.
Start Date: March 21, 2016
Expected Completion Date: April 2017
Status: Construction is underway
Cost and Funding Source: $3.445 million - Optional One Cent Funds
A new station will be built to replace the current Fire Station #6 located on Valley Drive.  The existing Fire Station #6 lacks the needed space to house modern fire equipment.  The new fire station will include living quarters and apparatus bays which will be larger than they are at the existing station.

At the existing station, crews must use Valley Drive to back equipment into bays, which can create traffic relays.  The new station will have two access points; one on Iris Street and another on Valley Drive.  Fire crews will use the Valley Drive access to exit the station quickly.  The Iris Street access point will allow crews to enter the station and then use the station driveway to back into the bays.

The construction site will be fenced to control access.

June 21:  Footers have been installed.  Stem walls are being poured.  On July 23rd and 24th Valley Road and Iris Street will be restricted while water and sewer taps are completed.

July 21:  Site Utilities are being installed and masonry walls are being constructed.

August 25:  Site work continues with structural walls complete on the apparatus bays.  Building utilities are being installed and concrete work is beginning this week.




 

15th and Elm Street Improvements           
           Trench for Waterline replacement  Location: 15th and Elm Streets
Consultant/Contractor: Grizzly Construction, LLC
Start Date: July 5th (Tentative)
Expected Completion Date: October 2016
Status: Work will tentatively begin July 5th.
Cost and Funding Source: $1.328 million - One Cent Funds, water funds, and sewer funds.
Workers will start work on Elm Street from CY Avenue to 13th Street moving to 15th Street from CY Avenue to Spruce Street once work is complete.  Work will not begin on the sections bordering Dean Morgan Junior High until the end of school year.  Work will be done in 2 block sections with each section being closed to traffic.  Access will be maintained for residents.

June 21:  Work is tentatively set to begin July 5th.

July 21:  Storm sewer has been installed on Elm Street from 13th to 15th Street.  Water service work has been completed on 15th from Elm to Oak Streets.  Concrete work and road base course work is ongoing.

August 25:  Utility work is complete and the road is open on Elm Street from 15th Street to 13th Street.  Utilities are complete, but roadwork continues on Elm from Cy to 11th and this section is closed.  Elm Street from 11th Street to 12th Street and 12th Street from Ash Street to Elm Street are closed for a manhole replacement.

November 2:  Phase A (Elm from 15h to 13th and 12th to CY) has been completed.  Phase B (15th from Ash to CY) work will begin in the spring of 2017.



East 21st Street Improvements Project           
         Finished Sidewalk     Location: Beverly Street to McKinley Street
Consultant/Contractor: Hedquist Construction
Start Date: June 1, 2016
Expected Completion Date: November 2016
Status: Concrete repairs from Beverly Street moving west.
Cost and Funding Source: $1.55 Million - One Cent Funds, Water Funds, and Sewer Funds
This project includes comprehensive infrastructure improvements, including concrete repairs, waterline replacements (nearly all in project area), sewer line replacements (McKinley to Jackson), street reconstruction (1 block near McKinley and 1 block near Beverly), asphalt resurfacing, and traffic control. 

Jan 16:  The project has been completed between Beverly and Glendale and McKinley.  It will result in limited access to portions of East 21st Street at various times.  This project is currently in winter shutdown and should resume on or around April 1, 2017.  The project is scheduled for completion in mid-June of 2017.




 

Bryan Stock Trail Bridge Replacement           
             Location: Soccer Blvd to Emigrant Trail
Consultant/Contractor: Hedquist Construction
Start Date: February 1, 2016
Expected Completion Date: November 2016
Status: West bridge deck replacement underway
Cost and Funding Source: Managed by WYDOT
Jan 16:  Bryan Stock Trail Bridge has been replaced.  There will be a few minor items to be completed in the Spring of 2017.  Any traffic control notifications will be posted as soon as details are received fro WYDOT.

This project is managed by the Wyoming Department of Transportation (WYDOT) and the City of Casper does not direct any of the engineering, construction, or project management.  Please contact WYDOT with all questions at 307-473-3200.


 

Hogadon Lodge          
          Hogadon lodge construction   Location: Hogadon Ski Area, 2500 W. Hogadon Road
Consultant/Contractor: GH Phipps Construction of Wyoming
Start Date: June 1, 2016
Expected Completion Date: June 2017
Status: Construction Ongoing
Cost and Funding Source: Optional One Cent #14 Sales Tax allocated to the Hogadon Lodge
The Hogadon Ski Area Master Plan, completed in July 2013, recommended that a new lodge be built for year-round use, with the ability to accommodate different events.  The new lodge will include a kitchen/catering area, bar, seating areas with views of the surrounding mountain, administrative areas with conference rooms, equipment rental area, and areas for the Casper Mountain Racers and Casper Mountain Snow Sports School.

June 28: Building Foundation Work

July 21:  Concrete wall and footing foundation work nearing completion.  Utility work underway.

August 25:  Foundation work is nearing completion.  Structural steel construction is ongoing. 

November 2:  Foundation work is complete and structural steel is 90% complete.  Upon completion of structural steel the building will be enclosed for the interior work.

January 3: All roofing membrane work completed; all clearstory windows installed; interior drywall, metal wall paneling, electrical and HVAC ongoing.



 