Construction Updates

Please review our list of current construction projects.  We will provide updates periodically for each project.  You can contact the Engineering department with any questions you may have.  We can be reached at 307-235-8341.


Robertson Road North Pathway           
Robertson Road Pathway facing north Location: North on Robertson Road from Squash Blossom Road 
Consultant/Contractor: WWC
JTL Group, Inc., dba Knife River
Start Date: August 15, 2017
Expected Completion Date: September 15, 2017
Status: Pre-Construction
Cost and Funding Source: $420,000 - WYDOT Tap allocation and Platte River Parkway Trust One Cent allocation
Project includes installation of a new 10-foot wide concrete pathway to be constructed along Robertson Road from Squash Blossom Road north to the City of Casper's growth boundary (approx. 3500 linear feet).
           
August 8, 2017:  Construction will begin after August 15, 2017.  This date is to provide a construction buffer due to nesting bald eagles in the area.



English Avenue Street Improvements       

           
Location: English Avenue
Consultant/Contractor: Grizzly Excavating & Construction
Start Date: August 8, 2017
Expected Completion Date: September 15, 2017
Status: Construction is underway
Cost and Funding Source: $116,184 - One Cent Funds
Project includes 2 blocks of street re-surfacing, concrete repairs, storm sewer repairs and a short waterline replacement on English Avenue from Poplar Street to Glenn Road.

August 8, 2017: 
Traffic control setup and initial saw-cuts for waterline replacement at Glenn Road and then a small storm sewer improvements.



 

15th and Elm Street Improvements           
           Trench for Waterline replacement  Location: 15th and Elm Streets
Consultant/Contractor: Grizzly Construction, LLC
Start Date: July 5th (Tentative)
Expected Completion Date: September 2017
Status: Work will tentatively begin July 5th.
Cost and Funding Source: $1.328 million - One Cent Funds, water funds, and sewer funds.
Workers will start work on Elm Street from CY Avenue to 13th Street moving to 15th Street from CY Avenue to Spruce Street once work is complete.  Work will not begin on the sections bordering Dean Morgan Junior High until the end of school year.  Work will be done in 2 block sections with each section being closed to traffic.  Access will be maintained for residents.

September 5, 2017:  Street surfacing and striping is complete except for concrete utility collars that are still to be installed on 15th Street from Walnut Street to CY Avenue.



 

Hogadon Lodge          
          Hogadon lodge construction   Location: Hogadon Ski Area, 2500 W. Hogadon Road
Consultant/Contractor: GH Phipps Construction of Wyoming
Start Date: June 1, 2016
Expected Completion Date: June 2017
Status: Construction Ongoing
Cost and Funding Source: Optional One Cent #14 Sales Tax allocated to the Hogadon Lodge
The Hogadon Ski Area Master Plan, completed in July 2013, recommended that a new lodge be built for year-round use, with the ability to accommodate different events.  The new lodge will include a kitchen/catering area, bar, seating areas with views of the surrounding mountain, administrative areas with conference rooms, equipment rental area, and areas for the Casper Mountain Racers and Casper Mountain Snow Sports School.

June 8, 2017:  Inspections and substantial walkthroughs are being completed for the building.  Utility work is ongoing.


 

East 26th Street Improvements       
          Hogadon lodge construction   Location: East 26th Street - Sagewood Avenue to McKinley Street (8 Blocks)
Consultant/Contractor: Installation & Service Company
Start Date: August 8, 2017
Expected Completion Date: October 20, 2017
Status: Construction Underway
Cost and Funding Source: $354,360 - One Cent Funds
Project includes 8 blocks of street re-surfacing, concrete repairs, storm sewer upgrades, and some full depth street reconstruction near McKinley Street.  Scope of work will include saw-cuts and installation of new storm sewer near McKinley, Lanner, and Lennox, along with minor concrete repairs throughout the project area.

August 8, 2017:
  Traffic Control setup and initial saw-cuts for concrete replacements and storm sewer upgrades.  A short closure will occur within 1 week for storm sewer installation near McKinley Street Intersection.